[ARCHIVED] Progress Update - May 2016

The original item was published from May 13, 2016 10:18 AM to May 13, 2016 10:19 AM

Storm Pipe:

All of the storm pipe and storm structures are currently installed within the project limits.

Potable Water Main:

New potable water main and service lines are continuing to be installed at the intersection of Sarasota and Palmetto. The new segment of water main on Ocala Road is still being tested before being put into service. 

Roadway:

Road base and curb construction continues on Sarasota and Ocala roads between Bayview and Palmetto road. Restoration of irrigation and sod is still in progress within the project limits.

Street Lights:

The street lights and poles are being reinstalled as segments of roadway are paved.

May 13

[ARCHIVED] Progress Update - May 2016

The original item was published from May 13, 2016 10:18 AM to May 13, 2016 10:19 AM

Storm Pipe:

All of the storm pipe and storm structures are currently installed within the project limits.

Potable Water Main:

New potable water main and service lines are continuing to be installed at the intersection of Sarasota and Palmetto. The new segment of water main on Ocala Road is still being tested before being put into service. 

Roadway:

Road base and curb construction continues on Sarasota and Ocala roads between Bayview and Palmetto road. Restoration of irrigation and sod is still in progress within the project limits.

Street Lights:

The street lights and poles are being reinstalled as segments of roadway are paved.

May 13

[ARCHIVED] Progress Update - May 2016

The original item was published from May 13, 2016 10:18 AM to May 13, 2016 10:18 AM

Storm Pipe:

All of the storm pipe and storm structures are currently installed within the project limits.

Potable Water Main:

New potable water main and service lines are continuing to be installed at the intersection of Sarasota and Palmetto. The new segment of water main on Ocala Road is still being tested before being put into service. 

Roadway:

Road base and curb construction continues on Sarasota and Ocala roads between Bayview and Palmetto road. Restoration of irrigation and sod is still in progress within the project limits.

Street Lights:

The street lights and poles are being reinstalled as segments of roadway are paved.